Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2016, Asso.subsea undertook transportation, installation, and protection of the 3‑pole 150 kV composite submarine power cable on the Cyclades Project segment between Syros and Paros (approx. 46.9 km), with Hellenic Cables as cable supplier and IPTO (ADMIE) as the client, marking the start of physical cable installation for this interconnection link within Cyclades Phase A.