Cyclades Interconnection Phase A : Lavrio (Mainland) - Siros
21 November 2014
Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
As part of the EU state-aid decision for the Cyclades Interconnection Phase A, a works breakdown allocated a budget of €100 million for the 150 kV underground and submarine cables connecting Lavrio with Syros and associated works on Syros, within a first-stage package totalling €159 million. This budget definition established the specific cost envelope for the Lavrio–Syros interconnector segment inside Phase A.