Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2016, Asso.subsea completed cable transportation, installation and protection for the Cyclades Project Syros-Paros segment. The scope comprised 46,910m of 3-pole 150 kV composite submarine power cable laid at up to 105m water depth, with Hellenic Cables as cable supplier and IPTO (ADMIE) as client.