Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In November 2020, Croatian transmission system operator HOPS signed a contract with KONČAR – Montažni inženjering (KMI) for the supply and laying of 110 kV submarine cables on the Crikvenica – Krk (Konjin) route, as part of a project that also covers the Dugi Rat – Brač (Postira) link. The agreement, valued at 91 million kuna for the first two sections and led by Končar engineering, aims to replace ageing oil‑paper insulated cables with new XLPE-insulated cables to improve the security of electricity supply to Adriatic islands.