Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Hrvatski operator prijenosnog sustava (HOPS) and KONČAR - Inženjering completed the first phase of the 110 kV subsea cable replacement project by finishing installation of the northern submarine cable section between the mainland and the island of Krk, covering the Crikvenica–Konjin route with new XLPE-insulated 3x 630 mm² cables that replace the existing link.