Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In early February 2024, Končar - Inženjering and the Croatian transmission system operator HOPS began the second stage of their 110 kV submarine cable replacement programme, initiating works to replace existing subsea cables including the 1 km Osor Bay crossing that links Cres and Lošinj with a new three-core XLPE-insulated cable. This stage covers nearly 30 km of cables between several Adriatic islands, with the Cres–Lošinj Osor section explicitly identified as part of the scope.