Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2023, under a contract from Prysmian Group, Correll Group executed the pull-in, termination and testing of two approximately 17.5 km, 225 kV HVAC export cables to the offshore substation platform for the 448 MW Courseulles-sur-Mer (Calvados) offshore wind farm. The scope covered pulling in both export cables, completing permanent hang-offs, routing and terminating the high-voltage and fibre-optic cores into the gas-insulated switchgear and fibre enclosures, and conducting post-installation tests from the onshore substation to the offshore assets.