Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
RTE plans to launch the main tender on 15 March 2024 for the contract covering three 750 MW HVAC offshore substations located 40–50 kilometres offshore, which will connect the Southern Brittany AO5 floating wind project and two Mediterranean floating wind farms to the onshore grid. This tender follows the pre‑qualification phase and is aimed at pre‑selected suppliers competing to deliver the offshore substations, including the Bretagne Sud AO5 platform.