Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +1yr (May 2026): RTE’s project page indicates the start of Bretagne Sud grid-connection works is envisaged in 2027. Offshore works (shared 750 MW platform) cannot start materially earlier than the overall raccordement works start; therefore move offshore construction start from 2026 to 2027 to align with RTE’s updated schedule. --- Offshore grid connection works for the Bretagne Sud area, including construction of the bottom-fixed HVAC offshore substation jacket and topside that will collect and export power from the Pennavel floating wind farm and the future 500 MW AO9 project, are planned by RTE to begin in 2026.