Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By 13 June 2022, the high‑resolution (UHR) seismic and multibeam echosounder geophysical survey for the BRE_AO5 offshore substation area had been completed, with Tecnoambiente and Geoquip Marine delivering the "UHR Seismic Survey Results Report" for the French Ministry for the Ecological Transition. The report presents processed MBES bathymetric grids, seismic profiles, interpreted geology, and geohazard assessment for the planned Bretagne Sud (AO5) offshore substation site, confirming completion of geophysical data acquisition and interpretation to inform design of the grid connection platform and associated export cables.