Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 26 June 2020 it was disclosed that installation of the Borssele Beta export cable would cost TenneT an additional EUR 50 million due to unforeseeable unstable soil conditions along the cable route, increasing the value of the NKT/VBMS subsea cable installation contract for Borssele Alpha and the Borssele Beta scope from EUR 160 million to EUR 210 million.