Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Boskalis' 2018 CSR report states that in 2018 the company began work on TenneT's Borssele Alpha project export cable. Together with Boskalis' 2016 contract press release describing pre-sweeping and dredging in the cable route, this indicates offshore site preparation (including pre-sweeping and route preparation) started during 2018.