Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Boskalis Subsea Cables completed the offshore export and inter-array cable installation for the Blyth Offshore Demonstrator, including lay and burial of approximately 14 km of 66 kV subsea cables and the shore-end landing at Cambois Bay, within the 2017–2018 project period, with completion falling in 2018.