Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
As part of its 2017–2018 works on the Blyth Offshore Demonstrator export and inter-array cable system, Boskalis Subsea Cables performed termination and testing of approximately 14 km of 66 kV subsea cables and accessories to verify the integrity of the transmission links between the offshore arrays and the onshore grid connection at Cambois Bay.