On 19 September 2014, the Haliade 150‑6 MW turbine at the Belwind facility exported its first energy to the grid, initiating a careful ramp‑up programme during which all systems were extensively tested. Alstom indicated that assembly and early tests were used to optimise offshore installation and commissioning procedures, with further tests planned to validate performance in real sea conditions.