Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 28 August 2025, Ocean Winds signed an agreement appointing Tele-Fonika Kable as the supplier of the BC-Wind onshore export cable system in Poland, covering the design, production and delivery of an approximately 8 km onshore export cable section connecting the landfall point in Choczewo municipality with the onshore substation in the same area.