Enshore Subsea was awarded a six-year framework contract by Nexans under which it will install the Wadden Sea sections of the submarine cable systems for TenneT’s 2 GW offshore grid connection projects BalWin3, LanWin2, and LanWin4 in the German North Sea. The shallow-water Wadden Sea installation campaigns for these export cables are scheduled across 2027, 2029, and 2030, providing the nearshore portions of the HVDC export routes that will transmit 2 GW from each project to the German mainland.