Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
By 12 March 2026, PGE Polska Grupa Energetyczna had fulfilled the conditions of its earlier conditional agreement and completed the acquisition of the FEW Baltic II offshore wind project from RWE, thereby taking over the 350 MW project to combine it with the 975 MW Baltica 9 site into the Baltica 9+ complex of about 1.3 GW. The transaction makes PGE the developer of both Baltica 9 and FEW Baltic II and is intended to capture economies of scale and support PGE’s 4 GW offshore wind target for 2035.