Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 7 April 2021, the President of the Polish Energy Regulatory Office awarded a Contract for Difference to the Baltica 3 and Baltica 2 offshore wind farms with a combined capacity of up to 2.5 GW, confirming their selection in Poland’s first offshore wind support round and setting the CfD strike price at the maximum level of PLN 319.60/MWh (about EUR 67.93/MWh). This revenue support decision significantly de‑risked the Baltica 3 project by guaranteeing a long‑term reference price for its future power generation, subject to final approval by the European Commission.