Transport, laying and burial of about 300 km of 275 kV export cables (four export cables) for Baltica 2; scope also includes boulder removal and seabed preparation works for the cable routes.
Boskalis was contracted by Ørsted and PGE Group to perform transport, laying and burial of the subsea export and inter-array cables for the Baltica 2 offshore wind farm. The scope included seabed preparation activities for the planned cable routes, including boulder removal, seabed levelling and pre-trenching to enable subsequent cable installation and protection. Reported scope included installation of four 275 kV export cables totalling about 300 km and more than 150 km of array cables, with preparatory works scheduled to start in 2025 and cable transport/installation planned for 2027.