Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of the 107 Siemens Gamesa 14 MW turbines at the Baltica 2 offshore wind farm is planned to start in 2027, after foundations, export cables, offshore substations, and inter-array cables have been installed and tested. Turbine erection in 2027 is part of the schedule to deliver first power and full commissioning of the 1.5 GW project the same year.