Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 22 December 2025, construction of the Baltica 2 export grid’s onshore substation at Osieki Lęborskie in the Choczewo commune was well advanced. A consortium of GE Vernova and Polimex Mostostal was executing works on the nearly 13‑hectare site, with main civil works completed, installation of 275 kV and 400 kV gas‑insulated switchgear buildings under way, and busbar and gantry structures linking the node to transmission operator PSE’s network already erected. In parallel, horizontal directional drilling works near the coastline were progressing to connect the offshore 275 kV export cables with the approximately six‑kilometre onshore cable route to the substation, marking substantive progress on the onshore elements of the Baltica 2 export connection.