Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By mid‑February 2026, PGE and Ørsted had completed the first stage of seabed preparation for Baltica 2, with the BOKA Falcon vessel having prepared 150 km of inter-array cable routes. The campaign included corridor clearance and trenching using the Megalodon plough, and work is now moving to prepare a 260 km export cable route ahead of later cable installation.