Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In August 2025, Boskalis began offshore site preparation for the Baltica 2 offshore wind farm, starting boulder clearance and corridor preparation along the planned inter-array and export cable routes. Using the vessel BOKA Falcon with the T‑Rex plough, the contractor cleared the seabed following geotechnical and UXO surveys, initiating the seabed preparation campaign ahead of cable trenching and installation.