NKT commenced large-scale production of the 230 kV offshore export power cables for the Baltic Power export system at its Cologne factory in June 2023, initiating a manufacturing campaign that is expected to run for about two years as part of its scope to deliver approximately 130 km of export cables and accessories for the project.