Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
For the Baltic 1 offshore grid connection, the offshore transformer platform that steps up the wind farm’s output from 33 kV to 150 kV was engineered and supplied by several contractors: Balslev designed and simulation-tested the platform, ABB provided the power distribution equipment, and Waserwind supplied the substation platform structure itself, while 50Hertz and NKT Cables handled the subsea cable supply and grid connection to shore.