Energinet.dk… work had to be pushed back… due to an error in NKT’s replacement cables… risk of error in the first 400 meters… and the last 4 km before the substation.
During operations, Energinet.dk worked with the supplier, NKT Cables, on a planned replacement of two subsea export cable sections after identifying a risk of faults near the landfall at Grenå and near the offshore substation. The replacement scope was described as the first 400 metres from Grenå and the last 4 km before the offshore substation; the work was postponed due to an error/failure in NKT’s replacement cable preparation.