Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Energinet.dk selected NKT Cables to supply and install the single about 24 km, 245 kV three‑core AC submarine export cable that transmits the aggregated output from the Anholt offshore substation to the onshore substation and into the Danish 220 kV grid.