Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
According to DEDDIE’s network development appendices, the Andros–Tinos 20 kV submarine interconnection consists of two 3×150 mm² aluminium cables, spanning a 3.3 km sea distance with a total installed cable length of 6.6 km, and has a recorded year of laying of 1974, indicating completion of the cable installation in that year.