The replacement 12 kV submarine cable to Agersø and Omø was energised in 2012 following SEAS-NVE Holding's 2011 supply tender (delivery deadline 31 July 2012 per the NKT Cables CPV 31321220 procurement record). The cable replaced the approximately 50-year-old existing link and restored full electrical supply to both islands via the Cerius (formerly SEAS-NVE) distribution network. Used 2012-07-31 as the commissioning month based on the supply tender's explicit delivery deadline; the exact in-service date is not published in Danish public procurement records but the replacement was substantially complete by end of 2012 summer. A fibre optic cable was co-laid with the power cable during the same campaign, confirming completion of both utility services at the same time.