UK — The Crown Estate Offshore Wind Leasing Round 5: Celtic Sea Floating (2023-2025)
1. At a glance
| Auction type | Seabed leasing — online ascending clock auction with exit bids + direct-award fallback for unallocated PDAs |
| Awarding body | The Crown Estate |
| Site model | Pre-identified Project Development Areas (PDAs) — 3 × 1,500 MW = 4.5 GW total across 1,000 km² of Celtic Sea seabed off South Wales and South West England |
| Technology | Floating offshore wind (first UK commercial-scale floating leasing round) |
| Pre-qualification | PQQ — technical, financial, legal |
| ITT Stage 1 | Technical criteria (consenting + stakeholder engagement + construction + O&M + decommissioning + social/environmental plans — apprenticeships ≥3.5%, NEETs ≥10% for 19-24 age group, skills development, community impact) — pass/fail, no maximum number of bidders advancing to Stage 2 |
| ITT Stage 2 | Online ascending clock auction — 3 PDAs auctioned simultaneously via a series of discrete Auction Rounds with Crown-Estate-set Auction Prices incrementing each round |
| Auction mechanics | In each Auction Round, each active Bidder submits a single Option Fee Bid for one PDA at the then-current Auction Price. Bidders can switch PDAs between rounds. A Bidder who chooses not to bid at the current Auction Price must submit an Exit Bid (maximum Option Fee they are willing to pay for a given PDA, bounded below the current round's Auction Price and above the previous round's price), and cannot re-enter. The auction ends when no more than one Bidder is willing to meet the Auction Price for each PDA |
| Award criterion | Highest Option Fee Bid (or Exit Bid) per PDA, subject to MLOC cap |
| MLOC cap | Maximum Level of Cash — a per-Bidder financial cap on maximum Option Fee Bid, calculated as MLOC ≥ (3 × Option Fee Bid × 1,500 MW) + (1.5 × £30m annual development costs). Used as a threshold at ITT Stage 1 and as a cap during ITT Stage 2. |
| Consenting delay discount | Post-year-6 50% option-fee reduction per IM §3.4.3: after year 6, if the Project Company can demonstrate that an Option Notice would be served but for an unavoidable delay in obtaining a key project consent that has been applied for, subsequent Option Fees for the relevant capacity are reduced by 50% for as long as the delay continues, provided the Project Company uses all reasonable endeavours. NOT a general "50% per year of delay" rule. Not present in R4. |
| Auction window | June 2025 — three PDAs auctioned simultaneously |
| Auction outcome (June 2025) | Two PDAs awarded via auction: PDA 1 to Gwynt Glas (EDF Renewables–ESB joint venture) and PDA 3 to Equinor. Per the Find a Tender notice, "two bidders remained at the final auction stage of the process and bid successfully for two of the PDAs" and "no tender was received for the third PDA" (PDA 2) — leaving PDA 2 unallocated via the auction. |
| Post-auction direct award | PDA 2 awarded to Ocean Winds (EDPR–ENGIE joint venture) via a switch to direct award under section 43 of the Procurement Act 2023 following the unsuccessful tendering procedure for PDA 2 at the June 2025 auction. Ocean Winds selected as preferred supplier on 19 November 2025, AfL signed 3 March 2026. This is a subsequent procurement response to an unsuccessful tender, NOT a pre-built auction rule fallback. |
| Final clearing Option Fee | £350/MW/year (excluding VAT) — all three winners pay the same rate, confirmed by the Crown Estate's 19 November 2025 announcement. This suggests the auction closed at or very near the starting Auction Price set by the Crown Estate — the clock did not ascend materially because bidder demand relative to PDAs (3 PDAs on offer, apparently fewer-than-3 bidders willing to pay more than £350/MW/year) caused early auction closure. |
| Lease term | 60 years Wind Farm Lease (same structure as R4) |
| Full capacity delivered through R5 | 4.5 GW once all three AfLs sign |
| Expected jobs and economic impact | ~4,000 construction phase jobs, ~£300m annual UK economic activity during construction, up to £19bn total forecast investment, >5,000 jobs total once fully delivered per Crown Estate analysis |
| Downstream pairing | Same as R4 — winners must compete in subsequent UK CfD Allocation Rounds for revenue; commercial dependency, not legal prerequisite |
| Headline significance | First UK commercial-scale floating wind leasing round; introduced clock auction format for Crown Estate seabed leasing; demonstrated a real-world use case for direct-award fallback when an auction does not exhaust the available sites |
Sources (4 primary): information-memorandum (69 pages, December 2023); faq (13 pages, February 2024); spring-2025-update (3 pages, ~March 2025); tce-third-site-announcement-nov-2025 (Crown Estate announcement of Ocean Winds award, 19 November 2025).
2. What makes Round 5 structurally different from R4 and from the four earlier pilots
| Dimension | UK CE R4 | UK CE R5 |
|---|---|---|
| Technology | Fixed-bottom offshore wind | Floating offshore wind (first UK commercial-scale) |
| Site type | Pre-refined Bidding Areas with multiple Eligible Projects proposed by Bidders | Pre-identified Project Development Areas — 3 PDAs pre-defined by The Crown Estate, bidders do not propose their own project boundaries |
| Number of sites | 4 Bidding Areas → 6 winning projects (7.98 GW) | 3 PDAs → 3 winning sites (4.5 GW) |
| Auction format | Multi-cycle DAILY SEALED bid | Online ascending clock auction with exit bids |
| Competitive dimension | Option fee (£/MW/year) | Option fee (£/MW/year) — same metric, different price-discovery mechanism |
| Auction simultaneity | One project awarded per daily Bidding Cycle in series | All 3 PDAs auctioned simultaneously in parallel rounds — a bidder can switch which PDA they bid on between rounds |
| Exit mechanism | None (daily sealed cycles) | Exit Bid — a bidder who chooses not to bid at the current Auction Price for any PDA must exit the auction entirely, submitting an Exit Bid (≤ current round's price, > previous round's price) that represents their reservation price; exiting bidders may still be allocated a PDA at their Exit Bid value if no other bidder emerges |
| Tiebreak | Cascading eligibility waterfall | No explicit tiebreak — the clock-auction mechanics are expected to produce unique winners by construction (ties resolved by the Exit Bid mechanism) |
| MLOC cap | 5-step cascading eligibility cap including cash availability, Corporate Group Capacity Limit, 3-project cap, Bidding Area cap, 5 km overlap | Single MLOC formula — MLOC ≥ (3 × Option Fee Bid × 1,500 MW) + (1.5 × £30m development costs). Used as a threshold at ITT Stage 1 and as a cap during ITT Stage 2 on maximum Option Fee Bid. No explicit 3 GW or 3-project cap — the PDA structure (3 × 1.5 GW = 4.5 GW total) provides an implicit cap |
| Fallback if auction fails to clear | Bidding Cycles simply continue until capacity target met | Direct award process under Procurement Act 2023 for any unallocated PDA — the Crown Estate actively engages the market post-auction to find a developer. Ocean Winds was awarded PDA 3 via this fallback in November 2025 — 5 months after the June auction |
| Consenting risk sharing | None stated in Information Memorandum | 50% option fee reduction per year of consenting delay — a risk-sharing feature that reduces the developer's financial exposure if project consenting is delayed through no fault of the developer |
| Non-price commitments | Hybrid project option, innovation discount, standard PQQ criteria | Apprenticeships ≥3.5% of workforce; NEETs ≥10% of 19-24-year-old new workers; Skills development plan; Community impact plan; Supply chain plan; Ports commitments — these are qualification gates at ITT Stage 1 (pass/fail), not weighted scoring dimensions, but they are stricter than R4's commitments |
| Grid connection approach | Developer-built with divestment to OFTO | Plan agreed in advance with NESO for connecting the sites to the GB grid — Crown Estate derisked the grid question by pre-negotiating the connection points and capacity before auction opening |
| Technical and environmental surveys | Developer responsibility post-AfL | Crown Estate undertook pre-consent surveys — a major programme of technical and environmental surveys before the auction opened, to reduce developer due diligence burden |
3. The R5 auction mechanism in detail
3.1 Online ascending clock auction with exit bids
Per the R5 Information Memorandum §3.4:
ITT Stage 2 will identify successful Bidders for each PDA via an online ascending clock auction (referred to as the Auction). All three PDAs will be auctioned at the same time during a series of discrete Auction Rounds.
During each Auction Round, Bidders will be able to submit a single Option Fee Bid in respect of any one PDA at the then current Auction Price specified by The Crown Estate for the relevant PDA in that Auction Round.
Any Bidder who chooses not to submit an Option Fee Bid at the then current Auction Price for any of the PDAs in an Auction Round will have to exit the Auction for all of the PDAs. A Bidder exiting the Auction must submit an Exit Bid, representing the maximum Option Fee that the Bidder would be willing to pay in respect of a given PDA.
Subject to the detailed Auction rules which will be issued at ITT Stage 1, the Auction will end when there is no more than one Bidder who is willing to meet the Auction Price for each PDA in any given Auction Round (i.e. a maximum of one Bidder willing to meet the live Auction Price for each individual PDA in an Auction Round). At that point, the Auction will end and Preferred Bidder status will be awarded to those Bidders who submitted Option Fee Bids at the Auction Price or the highest Exit Bid in the final Auction Round for the relevant PDA.
Mechanical interpretation:
- The Crown Estate sets a starting Auction Price for each PDA (apparently £350/MW/year — this is the final clearing price all three winners paid).
- In each round, bidders can bid for at most one PDA at the current Auction Price.
- Between rounds, the Crown Estate informs bidders how much the Auction Price will increase for the next round.
- A bidder who doesn't want to bid at the new price must exit the auction entirely and submit an Exit Bid indicating the maximum option fee they would pay (bounded by the previous round's price as a floor).
- The auction continues until each PDA has at most one bidder willing to meet the current Auction Price. At that point, the auction ends and Preferred Bidders are awarded:
- If a PDA has exactly one bidder at the current Auction Price → that bidder wins at the Auction Price.
- If a PDA has zero bidders at the current Auction Price but has an Exit Bid → the highest Exit Bid wins the PDA at the Exit Bid price.
- If a PDA has zero bidders and no Exit Bid → the PDA is unallocated and the Crown Estate falls back to the direct-award process.
June 2025 outcome: two of three PDAs cleared via the auction (Equinor and Gwynt Glas/EDF-ESB JV at £350/MW/year) and the third PDA was unallocated — meaning either (i) no bidder submitted a bid at the starting Auction Price for that PDA, or (ii) bids were withdrawn during the auction process. The Crown Estate then initiated the direct-award process and selected Ocean Winds in November 2025 at the same £350/MW/year rate.
3.2 The direct-award fallback
The R5 auction is the first pilot in the set to have an explicit non-auction fallback for unallocated sites. Per the Crown Estate's 19 November 2025 announcement:
Following the auction, The Crown Estate stated it would ensure the delivery of the full potential capacity of up to 4.5 GW available through Round 5 through deployment of a third site. Since then, it has been actively engaging the market to secure a developer for the third site, with Ocean Winds successful following a direct award process in accordance with the Procurement Act 2023.
The direct-award process is not part of the auction mechanics — it is a separate procurement procedure the Crown Estate conducts under a different legal basis (Procurement Act 2023 rather than a negotiated procedure). The Ocean Winds award terms match the auction clearing price (£350/MW/year, 1,500 MW, same AfL-to-Lease structure), suggesting the Crown Estate used the auction outcome as a price anchor for the direct-award negotiation. This is effectively a price-setting auction followed by a supply-expansion negotiation — a mechanism that makes the auction robust to bidder shortage without re-running the whole auction.
3.3 The MLOC cap as ITT Stage 2 competitive ceiling
A distinctive R5 feature: the Maximum Level of Cash (MLOC) calculated at ITT Stage 1 based on the Bidder's audited financials serves as a cap on the maximum Option Fee Bid the Bidder can submit during the auction. The formula is:
$$ \text{MLOC} \geq (3 \times \text{Option Fee Bid} \times 1{,}500\text{ MW}) + (1.5 \times £30\text{m annual development costs}) $$
This means a Bidder with an MLOC of £495m (for example) cannot bid more than £100,000/MW/year on any PDA, because (3 × 100,000 × 1,500) + (1.5 × 30m) = £450m + £45m = £495m. The cap is applied per-bidder, per-PDA, during the auction.
This is a financial-capacity-to-price-cap linkage — a mechanism that ensures only bidders with demonstrated financial resources can bid high, preventing unserious high bids from winning. The cap is calculated at ITT Stage 1 based on the Bidder's audited financials and is fixed for the duration of the auction.
3.4 Non-price qualification gates
R5 bidders must commit (at ITT Stage 1, pass/fail) to onshore social and environmental commitments:
- Apprenticeships plan: ≥3.5% of new workers employed as apprentices
- Skills development plan: identify skills gaps + plan to address them
- NEETs plan: ≥10% of all new workers aged 19-24 must be (or have recently been) NEETs — Not in Education, Employment or Training
- Community impact plan: active engagement with potentially affected communities
- Ports plan: identify ports intended for assembly/deployment (Port Talbot and Port of Bristol are identified as likely locations)
These are mandatory qualification gates, not weighted scoring dimensions. All bidders must commit to them to qualify. A bidder who fails to provide credible plans fails ITT Stage 1 and cannot proceed to the auction. The plans become contractual commitments under the Wind Farm AfL / Lease — enforceable by the Crown Estate throughout the development and operating life of the project.
Contrast with Carolina Long Bay bidding credits: R5's non-price commitments are pass/fail gates, not price-discount dimensions. They do NOT affect the competitive bid amount; they are a floor that all bidders must clear. Carolina Long Bay's bidding credits, by contrast, allowed a bidder to claim a discount on their winning bid based on commitments made — the commitments translated directly into price reductions. R5's commitments translate into qualification passes, not price impacts.
4. The three R5 winners
| PDA | Site | Capacity | Successful Bidder | Option Fee | Preferred Supplier Date | AfL Signed | Award Mechanism |
|---|---|---|---|---|---|---|---|
| PDA 1 | Celtic Sea | 1,500 MW | Gwynt Glas (EDF Renewables – ESB joint venture) | £350/MW/year (excl. VAT) | 19 June 2025 | October 2025 | Auction |
| PDA 2 | Celtic Sea | 1,500 MW | Ocean Winds (EDPR – ENGIE 50-50 JV) | £350/MW/year (excl. VAT) | 19 November 2025 | 3 March 2026 | Section 43 switch to direct award under Procurement Act 2023 after "no tender received for this PDA" at the June auction |
| PDA 3 | Celtic Sea | 1,500 MW | Equinor | £350/MW/year (excl. VAT) | 19 June 2025 | October 2025 | Auction |
| Total | 4,500 MW | 3 winners | £350/MW/year uniform | Mixed |
Gwynt Glas and Equinor signed Agreements for Lease in October 2025. Ocean Winds signed its AfL on 3 March 2026.
Why £350/MW/year uniform
All three winners pay the same option fee rate — a striking outcome that contrasts sharply with R4's dramatic price spread (£76,203 – £154,000/MW/year). The uniformity suggests:
- The auction closed at or very near the starting Auction Price. The Crown Estate set £350/MW/year as the opening Auction Price and the clock did not materially ascend — bidder demand was thin enough that the auction cleared before any price discovery in higher rounds.
- The direct-award for PDA 3 intentionally matched the auction clearing price — the Crown Estate had an implicit obligation not to give Ocean Winds preferential terms relative to Equinor and Gwynt Glas.
- R5's option fee is substantially below R4's — even the lowest R4 option fee (RWE at £76,203/MW/year for Dogger Bank) is 218× higher than R5's £350/MW/year. This reflects: (i) floating wind's earlier technology maturity and higher project-level risk; (ii) R5's deeper site waters and less-developed supply chain; (iii) thinner bidder competition in a nascent market; (iv) Crown Estate's deliberate choice of a lower starting Auction Price to encourage participation in a derisking round.
The 50% option fee reduction for consenting delays further reduces the effective option fee, making R5 substantially cheaper than R4 on a £/MW/year basis even before accounting for the technology risk premium.
5. Timeline
| Date | Event |
|---|---|
| December 2023 | Information Memorandum published — tender formally announced |
| February 2024 | FAQ published |
| 2024 | PQQ process |
| Q1 2025 | ITT Stage 1 |
| March 2025 | Spring 2025 Update published |
| June 2025 | ITT Stage 2 auction runs — 2 of 3 PDAs awarded |
| June 2025 | Preferred Bidders announced: Equinor, Gwynt Glas |
| October 2025 | Equinor and Gwynt Glas sign Agreements for Lease |
| 19 November 2025 | Ocean Winds announced as third winner via direct award under Procurement Act 2023 |
| Spring 2026 | Ocean Winds AfL expected to sign |
| 2029-2035 | Consenting, FID, construction phases |
| Late 2030s | Commissioning and operational start |
7. Schema implications — what R5 adds beyond R4 and the four original pilots
Preliminary observations for the R5 validation summary:
-
Ascending clock auction with Exit Bids — a specific auction mechanic that v0.5's Axis 2
bid_formatdoesn't yet enumerate. The Exit Bid mechanism is interesting because it creates a deferred-acceptance structure: a bidder who exits can still win at their Exit Bid price if the clock fails to generate a competing live bid. This is not quite the same as US NY Bight's exit bid (which is single-lease and within-round), nor the same as the German dynamic bidding procedure's Zwischenrunden-Gebote (which are intra-round mid-level bids). R5's Exit Bid is an explicit bidder-level mechanism for graceful exit with residual eligibility. -
Direct-award fallback under Procurement Act 2023 — a non-auction fallback process that runs after the auction concludes. The schema needs to express this as a separate auction record or as a
fallback_mechanismsub-structure on Axis 8's process stages. v0.5 does not model non-auction award paths. The direct-award is a distinctauction_type(or perhapsaward_type) rather than an auction mechanism per se. -
Consenting-delay option-fee discount — a mechanism that reduces the winner's prize_consideration obligation by 50% per year of delay. This is not simply a penalty (like Thor's defective-performance penalty) — it's a developer-friendly discount that kicks in when project risks materialise beyond the developer's control. v0.5's prize_consideration structure does not have a
delay_discount_schedulefield; this is a candidate addition for v0.6. -
Non-price qualification commitments with quantitative thresholds — apprenticeships ≥3.5%, NEETs ≥10%. These are quantitative qualification gates, not binary pass/fail gates. v0.5's Axis 3 supports binary gates cleanly but the quantitative threshold structure (e.g. "≥3.5%") may need a
qualification_gate.threshold_structuresub-field that distinguishesbinary | quantitative_minimum | quantitative_maximum | range. -
MLOC-as-price-cap — R5's MLOC is both a qualification threshold (at ITT Stage 1) AND a cap on maximum bid (during ITT Stage 2 auction). This is a dual-use financial constraint that v0.5 doesn't explicitly model. The qualification-gate aspect fits Axis 3 cleanly, but the bid-cap aspect fits Axis 2's
bid_format— the same financial parameter gates entry AND constrains bid behaviour. Schema: afinancial_parameter_linksstructure showing that Axis 3 gate N is linked to Axis 2 bid-cap M. -
Uniform clearing price outcome — all three R5 winners paid the same option fee (£350/MW/year). This is unusual enough to be worth capturing in the validation summary, but it's not a schema addition — it's an observation about the competitive outcome. The schema already supports this via Axis 2's clearing-price data.