French Offshore Wind Grid Connections[Draft]

How offshore wind transmission assets are planned, constructed, and financed in France under the centralised RTE TSO-build model.

Last updated: March 2026 · Sources: RTE, CRE, DGEC, MTE · Fact-checked 2026-03-15 (2 iterations)

Operational Capacity~1.5 GW
2035 Target (PPE3)15 GW
Grid Investment by 2040€37B (RTE)
Grid Systems in Pipeline22

Key Regime

TSO-Build Model RTE (sole TSO, 100% EDF subsidiary) builds, owns, and operates ALL offshore grid connections. Developers only build the wind farm.

Key Bodies

RTECREDGECMTECNDPOFB

Key Regulatory Bodies

BodyRoleKey Functions
CREEnergy regulatorAdvises on tender specifications, instructs bids, proposes winners to minister. Sets TURPE network tariff. Examines RTE’s SDDR grid plan. Evaluates public-service charges
RTETransmission system operatorSole TSO. Finances, builds and operates offshore grid connections (AO3 onward). Publishes SDDR (10-year grid plan). 100% EDF subsidiary
DGECEnergy policy directorate (joint MTE/MESR competence since Oct 2024)Drafts energy policy (PPE), coordinates offshore wind tenders, sets capacity targets, implements EU directives
MTEEnvironment & energy ministry (joint DGEC competence since Oct 2024)Environmental authorisation for offshore projects, maritime spatial planning (DSF), biodiversity oversight, co-stewards energy policy with MESR
Préfecture MaritimeMaritime authorityMaritime domain authorisation (concession d’utilisation du DPM), navigational safety, maritime zone management
CNDPPublic debate commissionOrganises mandatory public debate (débat public) for major infrastructure projects. Debates typically last 4–6 months
Autorité EnvironnementaleEIA review bodyReviews environmental impact assessments, issues advisory opinions on offshore wind and grid connection projects
OFBBiodiversity agencySpecies and habitat protection, marine biodiversity monitoring, consultee for offshore permits

Primary Regime TSO-Build Model

France operates a centralised TSO-build model for offshore wind grid connections. RTE, as Frances sole transmission system operator, is responsible for designing, constructing, owning, and operating all offshore grid connections from the offshore substation to the onshore grid connection point. Wind farm developers are only responsible for the wind farm itself and inter-array cables to the RTE offshore substation.

Single TSO advantage: Unlike Germany (which has three offshore TSOs: TenneT, 50Hertz, Amprion) or the UK (where developers build transmission assets before transferring to OFTOs), Frances single-TSO model simplifies coordination but concentrates delivery risk on RTE.

How It Works

StepActorDescription
1. Maritime planningState (DGEC / MTE)Identifies suitable zones via Document Stratégique de Façade (DSF) maritime spatial plans
2. Public debateCNDPMandatory débat public for major offshore wind projects (4–6 months)
3. TenderCREInstructs bids, proposes winners to minister (appel d’offres). Since APER Law, tender can launch before debate concludes
4. Grid connectionRTERTE designs, procures, and constructs the offshore grid connection in parallel with wind farm development
5. Wind farmDeveloperWinning bidder builds the wind farm and connects to RTE’s offshore substation via inter-array cables

Comparison: France vs UK vs Germany

FeatureFrance (TSO-Build)UK (OFTO)Germany (Multi-TSO)
Who builds grid connectionRTE (sole TSO)Wind farm developerTSO (TenneT / 50Hertz / Amprion)
Who operates grid connectionRTE (permanent)OFTO (25-year licence)TSO (permanent)
Number of offshore TSOs1 (RTE)N/A (OFTO regime)3 (TenneT, 50Hertz, Amprion)
Cost recoveryTURPE network tariff (socialised)TNUoS charges (socialised)Offshore grid levy (socialised)
Grid connection riskRTE bears construction riskDeveloper bears construction riskTSO bears construction risk
Delay compensationCapped at 3 years equivalentN/A — developer owns assetTSO pays developer (§17e EnWG)
Site planningState-led (DSF zones)Developer-led (applies for connection)Centralised (BSH FEP)

Key Legislation

Law / InstrumentScope
Loi APER (March 2023)Acceleration of renewable energy. Allows tenders before public debate concludes. Streamlined permitting. Offshore wind acceleration measures
Code de l’environnementEnvironmental authorisation framework for offshore installations, EIA requirements, species protection
Code de l’énergieTSO obligations, grid connection duties, renewable energy support mechanisms (complément de rémunération)
PPE (Programmation Pluriannuelle de l’Énergie)Multi-year energy programme setting offshore wind capacity targets (PPE2: 2019–2028, PPE3: 2024–2035)
DSF (Document Stratégique de Façade)Maritime spatial plans for France’s 4 maritime façades. Identifies zones suitable for offshore wind
SDDR (Schéma Décennal de Développement du Réseau)RTE’s 10-year grid development plan. SDDR 2025 allocates €100B total, €37B for offshore grid

Tender System (Appels dOffres)

France allocates offshore wind capacity through a series of competitive tenders managed by CRE. The programme has evolved dramatically since the first round in 2012, with strike prices falling from over 200/MWh to below 50/MWh at Dunkerque (AO3).

Tender Rounds (AO1AO11)

RoundYearProject(s)CapacityStrike PriceStatus
AO12012Saint-Nazaire, Fécamp, Courseulles-sur-Mer~1.5 GW~€200/MWhOperational / commissioning
AO22013Saint-Brieuc, Île d’Yeu / Noirmoutier~1.0 GW~€200/MWhConstruction
AO32016Dunkerque600 MW€44/MWhConstruction
AO42021Sud-Atlantique (Oléron)1 GW€45/MWhDevelopment
AO52022Centre Manche 11 GW€45/MWhDevelopment
AO62022Bretagne Sud250 MW (floating)€140/MWhDevelopment
AO72024Oléron extension1.2 GWFailed (zero bids, Sep 2025)
AO82024Centre Manche 21.5 GW€66/MWhAwarded
AO92025Méditerranée (floating)250–500 MWTBCIn progress
AO102025Multi-zone mega-tender8.4–9.2 GWTBCConsultation launched Mar 2025
AO11TBCTBCTBCTBCPlanned
AO7 failure (September 2025): The Oléron extension tender received zero bids, mirroring similar failures in Germany and the UK. Contributing factors included environmental constraints, insufficient grid readiness, supply chain bottlenecks, and rising capital costs.
AO10 mega-tender (March 2025): Consultation launched for 8.49.2 GW across multiple zones by far the largest single allocation in French offshore wind history. Designed to provide pipeline visibility and economies of scale.

Tender Process Flow

French Offshore Wind Tender Lifecycle

Maritime Planning

State identifies zones via DSF

Débat Public

4–6 months

CNDP public consultation

Tender Launch

CRE instructs bids, proposes winners

Competitive Dialogue

Bidders and state refine specs

Award

Minister awards contract

Permitting

Env. auth + maritime licence

Construction

Developer builds farm, RTE builds grid in parallel

Since the APER Law (March 2023), CRE can launch the tender before the public debate concludes, accelerating the process by up to 12 months.

Price Evolution

Frances offshore wind strike prices have followed the global cost-reduction trend, though early rounds (AO1AO2) were among the most expensive globally at ~200/MWh. The AO3 Dunkerque tender (44/MWh, awarded 2019) marked a step change, with prices broadly stabilising in the 4466/MWh range for fixed-bottom projects. Floating wind remains more expensive (~140/MWh for AO6 Bretagne Sud).

Consenting & Permitting

Frances offshore wind consenting regime differs depending on whether the project is in territorial waters (012 nm) or the Exclusive Economic Zone (EEZ, 12200 nm). The APER Law (2023) introduced acceleration measures including the envelope permit concept.

Consenting Regimes

ZoneAuthorisations RequiredKey Features
Territorial Waters (012 nm)Two authorisations: environmental authorisation + maritime domain concession (concession DPM)Separate permits for installation and for use of public maritime domain. Préfet de région coordinates
EEZ (12200 nm)Single authorisation under Code de l’environnementSimplified single-permit regime. Préfet maritime coordinates with Préfet de région for onshore elements

Envelope Permit (Permis Enveloppe)

Introduced by the APER Law, the envelope permit allows projects to obtain environmental authorisation based on a range of technical parameters (e.g. turbine capacity 1220 MW, hub height 120160 m) rather than fixed specifications. This allows developers to select final turbine models later in the process without requiring a new permit.

Appeals

Appeals against offshore wind permits go directly to the Conseil d’État (Frances highest administrative court), bypassing lower courts a measure introduced to accelerate legal certainty. Early projects (AO1) faced multi-year legal challenges, with Saint-Nazaires permits ultimately upheld after 6+ years of litigation.

Environmental Impact Assessment

RequirementAuthorityNotes
Étude d’impact (EIA)Autorité EnvironnementaleMandatory for all offshore wind projects. Covers marine mammals, avifauna, benthos, seascape, fishing
Natura 2000 assessmentDREAL / OFBRequired when project intersects or neighbours a Natura 2000 site
Marine biodiversity monitoringOFBPre-construction baseline + operational monitoring. Key species: harbour porpoise, seabirds, bats
Public inquiry (enquête publique)PréfetMandatory post-EIA. Commissaire-enquêteur issues advisory opinion

Typical Timeline

PhaseDurationDescription
Maritime planning (DSF)2–3 yearsZone identification and strategic environmental assessment
Public debate (CNDP)4–6 monthsMandatory public consultation
Tender and award12–18 monthsCRE-managed competitive process
Permitting18–24 monthsEnvironmental authorisation, maritime domain concession, grid connection
Construction3–4 yearsWind farm + RTE grid connection in parallel
Total (zone to power)~79 yearsFrom zone identification to first power

Grid Connection & System Planning

SDDR 2025 (RTE Grid Development Plan)

RTEs Schéma Décennal de Développement du Réseau (SDDR) 2025 outlines 100 billion of total grid investment, of which 37 billion is allocated to offshore grid connections through 2040. This represents the largest infrastructure programme in RTEs history.

SDDR 2025 ParameterValue
Total grid investment€100B (2025–2040)
Offshore grid investment€37B (2025–2040)
Offshore grid connections planned22 systems
Peak construction period2028–2035

PPE3 Offshore Wind Targets

TargetCapacity
20304–5 GW installed
203515 GW installed
205040–45 GW installed (long-term ambition)
PPE3 target reduction: The initial consultation proposed 18 GW by 2035, but the final PPE3 target was set at 15 GW reflecting supply chain constraints and grid connection lead times.

Maritime Spatial Planning (DSF)

Frances maritime spatial planning is organised around four façades maritimes (maritime fronts), each with a Document Stratégique de Façade (DSF) that identifies zones suitable for offshore wind development.

FaçadeKey ZonesProjects
Manche Est – Mer du NordDunkerque, Fécamp, Courseulles, Centre MancheAO1 (Fécamp, Courseulles), AO3 (Dunkerque), AO5, AO8
Nord Atlantique – Manche OuestSaint-Brieuc, Saint-Nazaire, Bretagne SudAO1 (Saint-Nazaire), AO2 (Saint-Brieuc), AO6 (floating)
Sud AtlantiqueOléron, Île d’Yeu / NoirmoutierAO2 (Île d’Yeu), AO4 (Oléron), AO7 (failed)
MéditerranéeGolfe du Lion, EFGL pilotsAO9 (floating), pilot floating farms

Technology Transition

GenerationTechnologyCapacity per SystemProjects
CurrentHVAC 225 kV~500 MWAO1–AO3 projects
Near-termHVDC ±320 kV1–2 GWAO4–AO8 projects
FutureHVDC ±525 kV2+ GWAO10+ mega-tender projects

The transition from HVAC to HVDC is driven by increasing distances to shore and larger project capacities. RTEs first HVDC offshore connections are expected for the AO4AO8 generation of projects, with ±525 kV HVDC planned for future multi-GW zones.

Financial & Commercial Framework

Complément de Rémunération (CfD Mechanism)

French offshore wind projects are supported via a Contract for Difference (complément de rémunération) mechanism. The developer receives a guaranteed strike price: when the market price is below the strike price, the state pays the difference; when above, the developer pays back the surplus.

Strike Prices by Tender Round

RoundProjectStrike Price (€/MWh)Contract Duration
AO1Saint-Nazaire, Fécamp, Courseulles~20020 years
AO2Saint-Brieuc, Île d’Yeu / Noirmoutier~20020 years
AO3Dunkerque4420 years
AO4Sud-Atlantique (Oléron)~4520 years
AO5Centre Manche 1~4520 years
AO6Bretagne Sud (floating)~14020 years
AO8Centre Manche 26620 years

Grid Cost Allocation

ParameterDetail
Who bears grid connection costsRTE bears 100% of offshore grid connection costs
Cost recovery mechanismTURPE (Tarif d’Utilisation des Réseaux Publics d’Électricité) — network access tariff paid by all consumers
TURPE 7 offshore WACC5.5%
Developer costsInter-array cables from turbines to RTE offshore substation only
Delay compensationRTE compensates developers for grid connection delays, capped at 3 years equivalent revenue
TURPE 7 (20252028, effective February 2025): CRE set the offshore WACC at 5.5% for the TURPE 7 tariff period, providing RTE with regulated returns on its 37B offshore grid investment programme.

Bilateral & International Cooperation

North Seas Energy Cooperation (NSEC)

France is a founding member of the NSEC (established 2016). Members: Belgium, Denmark, France, Germany, Ireland, Luxembourg, the Netherlands, Norway, and the European Commission. France participated in the Hamburg Declaration (January 2026) committing to 100 GW of cross-border offshore generation capacity.

Key Bilateral / Cross-Border Projects

ProjectPartnersCapacityStatusNotes
Celtic InterconnectorFrance Ireland (RTE / EirGrid)700 MWUnder ConstructionHVDC interconnector. PCI status. Under construction, expected 2027. No hybrid offshore wind component
Bay of BiscayFrance Spain (RTE / Red Electrica)2 × 1 GWUnder ConstructionSubsea HVDC interconnector via Bay of Biscay. PCI status. No hybrid component
IFAFrance – UK2,000 MWOperationalExisting HVDC interconnector (1986). No hybrid component
IFA2France – UK1,000 MWOperationalHVDC interconnector (2021). No hybrid component
ElecLinkFrance – UK1,000 MWOperationalChannel Tunnel interconnector (2022). No hybrid component
No hybrid projects yet: Unlike Denmark and Germany, France has not committed to any hybrid offshore wind/interconnector projects to date. However, the Hamburg Declaration (January 2026) may catalyse future hybrid concepts, particularly in the Channel and Bay of Biscay.

Historical Evolution

  1. First offshore wind tender announced

    AO1 launched for three sites: Saint-Nazaire, Fécamp, and Courseulles-sur-Mer (~1.5 GW combined).
  2. AO1 awarded

    ~200/MWh strike prices awarded to EDF Renewables consortia. Beginning of multi-year legal challenges.
  3. AO2 launched and awarded

    Saint-Brieuc and Île dYeu / Noirmoutier (~1 GW). Similar ~200/MWh strike prices.
  4. AO3 Dunkerque tender launched

    Competitive dialogue format. Would eventually produce Frances lowest strike price at 44/MWh (awarded 2019).
  5. AO3 Dunkerque awarded at EUR 44/MWh

    Step change in French offshore wind economics. 600 MW awarded to EDF consortium. PPE2 published with offshore wind targets.
  6. Saint-Nazaire commissioned

    Frances first commercial offshore wind farm: 480 MW, 80 Haliade 150-6MW turbines. AO4 and AO5 tenders launched.
  7. Loi APER enacted (March)

    Acceleration of renewables law. Allows tenders before public debate concludes. Saint-Brieuc (496 MW) commissioned. Fécamp (497 MW) commissioned. Floating pilots operational: Groix & Belle-Île, EFGL.
  8. AO7 and AO8 tenders launched

    Courseulles-sur-Mer (448 MW) commissioned, bringing operational total to ~1.5 GW. AO6 Bretagne Sud floating tender awarded.
  9. AO7 fails; AO10 consultation launched

    September: AO7 Oléron extension receives zero bids. AO8 Centre Manche 2 awarded at 66/MWh. March: AO10 mega-tender consultation launched (8.49.2 GW). PPE3 finalised with 15 GW target by 2035.
  10. PPE3 implementation begins

    RTE SDDR 2025 published (37B offshore grid investment). Dunkerque (600 MW) construction advancing. Grid connection technology transition to HVDC underway.

Current Grid Connection Systems

Operational

ProjectCapacityTechnologyCommissioned
Saint-Nazaire480 MW225 kV HVAC2022
Saint-Brieuc496 MW225 kV HVAC2023
Fécamp497 MW225 kV HVAC2023
Courseulles-sur-Mer448 MW225 kV HVAC2024
Groix & Belle-Île (floating pilot)28.5 MW66 kV AC2023
EFGL (floating pilot)30 MW66 kV AC2023
Total operational~1.5 GW

Under Construction

ProjectCapacityTechnologyExpected
Dunkerque600 MW225 kV HVAC2027
Île d’Yeu / Noirmoutier496 MW225 kV HVAC2027–2028

In Development / Awarded

ProjectTenderCapacityTechnologyExpected
Sud-Atlantique (Oléron)AO41 GWHVDC ±320 kV2030–2031
Centre Manche 1AO51 GWHVDC ±320 kV2031–2032
Bretagne Sud (floating)AO6250 MWHVAC / HVDC2031–2032
Centre Manche 2AO81.5 GWHVDC ±320 kV2032–2033
Méditerranée (floating)AO9250–500 MWTBC2033+

Planned (AO10+)

ZoneCapacityTechnologyExpected
AO10 multi-zone mega-tender8.4–9.2 GWHVDC ±320/525 kV2033–2040
AO11+ future roundsTBCHVDC ±525 kVPost-2035

Capacity Summary

CategoryCountCapacity
Operational (fixed)4~1.9 GW
Operational (floating pilots)2~59 MW
Under construction2~1.1 GW
In development / awarded5~4.0 GW
Planned (AO10+)~9~8.4–9.2 GW
Total pipeline~22~15–16 GW
Government targets: 45 GW installed by 2030, 15 GW by 2035 (PPE3), and 4045 GW by 2050 (long-term ambition). The current pipeline of ~1516 GW aligns with the 2035 target but requires significant acceleration of tender awards and grid construction.

Supranational Dimension

EU Regulatory Framework

FrameworkRelevance to France
TEN-E Regulation (EU 2022/869)PCI/PMI designation for cross-border projects (Celtic Interconnector, Bay of Biscay). Cross-border cost allocation mechanisms
RED III (Revised Renewable Energy Directive)Not yet fully transposed into French law. Renewable acceleration area provisions. 42.5% RE target by 2030
EU Offshore RE Strategy (2020)EU target: 300 GW offshore wind by 2050. France allocated among Atlantic and Mediterranean basins
ENTSO-E ONDPOffshore Network Development Plan. France’s Atlantic and Channel connections included in Northern Seas and South-West corridors
NZIA (Net Zero Industry Act)Non-price criteria in tenders: sustainability, resilience, cybersecurity. France already uses qualitative criteria in offshore tenders

PCI Projects Involving France

ProjectStatusNotes
Celtic Interconnector (FRIE)Under ConstructionPCI status. CEF Energy co-financing. Under construction
Bay of Biscay (FRES)Under ConstructionPCI status. 2 × 1 GW HVDC. In development

NSEC Membership

France is a founding member of the North Seas Energy Cooperation. At the Hamburg Summit (January 2026), France joined the declaration targeting 100 GW of cross-border offshore generation. France has not yet committed to hybrid offshore wind/interconnector projects under the NSEC framework, but the declaration opens the door to future collaboration, particularly with the UK (Channel) and Spain (Bay of Biscay).

Regime Reform & Future Direction

PPE3 & Target Evolution

PPE3 (Programmation Pluriannuelle de l’Énergie, 20242035) set the offshore wind target at 15 GW by 2035, reduced from the initial 18 GW consultation figure. The reduction reflects supply chain constraints, grid connection lead times, and the AO7 tender failure. The long-term ambition remains 4045 GW by 2050.

AO10 Mega-Tender

The AO10 consultation (March 2025) proposes allocating 8.49.2 GW across multiple zones in a single mega-tender a fundamental shift from Frances previous approach of tendering individual 0.51.5 GW projects. This is designed to provide pipeline visibility for the supply chain and enable economies of scale in grid connection infrastructure.

Technology Transition to HVDC

All operational French offshore wind connections use HVAC 225 kV technology. The next generation of projects (AO4+) will require HVDC connections as capacities increase to 12 GW per project and distances to shore grow. RTE is developing its first offshore HVDC connections, with ±525 kV systems planned for the AO10+ generation.

Hybrid Projects

France has no hybrid offshore wind/interconnector projects in its current pipeline, unlike Denmark (Bornholm Energy Island) and Germany (planned DE-DK hybrids). The Hamburg Declaration (January 2026) may catalyse future hybrid concepts, particularly in the Channel (with the UK) and Bay of Biscay (with Spain), but no concrete projects have been announced.

Reform AreaStatus
PPE3 target15 GW by 2035 (reduced from 18 GW consultation)
AO10 mega-tenderConsultation launched March 2025 (8.4–9.2 GW)
AO7 failure responseUnder review. Tender design reforms expected
HVDC transitionFirst HVDC connections expected for AO4–AO8 projects (2030+)
RED III transpositionNot yet fully transposed into French law
Hybrid projectsNone committed; Hamburg Declaration may catalyse
Floating wind scale-upAO9 + future Mediterranean tenders. Technology maturing

Fact Check

This page was fact-checked using automated verification (OpenAI gpt-5.4 with web search). Two iterations were run against the research document, with findings independently verified before corrections were applied.

IterationDateErrors ReportedVerified & FixedFalse PositivesSummary
22026-03-151073DGEC/MTE attribution updated (Oct 2024 joint competence), La Mer en Débat figures corrected, TURPE 7 timing (Feb 2025) and 0.5% offshore premium confirmed, SDDR fiche title corrected, WindSeeG terminology removed.
12026-03-1518108Key fixes: RTE role narrowed to AO3-onward model, CUDPM opinion terminology, NSEC UK/Iceland wording, PPE3 45+ GW→45 GW, SNML 2022 entry removed, AO5 capacity 250→269.5 MW.
This reference is provided for informational purposes. Regulatory frameworks are complex and subject to change. Always consult primary sources and professional advisors for decisions. Last reviewed March 2026.