Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Following the Final Investment Decision for the Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm, Ocean Winds states that from spring 2024 maritime works will begin, including installation of the offshore electrical substation and the first submarine cables, and that at the same time RTE, responsible for the grid connection, will set up a double submarine connection to transfer electricity to the onshore grid; this marks the planned start of offshore construction for the Yeu‑Noirmoutier 225 kV export link.