Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Inter-array cable installation at the Windanker offshore wind farm is scheduled to start in the first quarter of 2026. Under its EPCI scope, Van Oord will design, supply and install around 29 kilometres of inter-array cables using its cable-laying vessel Nexus and trencher Dig-It to interconnect the 21 turbines and the offshore substation.