Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 October 2017, Iberdrola, together with turbine supplier Adwen and installation contractor Fred. Olsen Windcarrier, completed installation of all 70 AD 5‑135 wind turbines at the Wikinger offshore wind farm, using the jack-up vessel Brave Tern and a large team of technicians, thereby entering the final phase before commissioning.