Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 9 January 2017, ITW Performance Polymers had completed the grouting works for all 70 jacket foundations at the Wikinger offshore wind farm using its Ducorit S2 ultra-high‑performance cementitious material, concluding a campaign that ran from 26 July 2016 and formed the final stage of securing the jackets to their piles.