Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 2 March 2017, Prysmian had completed laying the inter-array cable system at the 350 MW Wikinger offshore wind farm, installing around 81 km of 33 kV submarine cables to connect the 70 turbines to the offshore substation under its turnkey contract for Iberdrola.