Support to installation and burial of the single HVAC export cable system between the Westermost Rough offshore substation and the onshore connection near Hedon (~11.8 km offshore section within a 27 km total route).
Boskalis Offshore worked alongside Visser Smit Marine Contracting on the Westermost Rough export cable installation package. In partnership with VSMC, Boskalis provided offshore construction support for the laying and burial of the export cable connecting the Westermost Rough offshore wind farm to the onshore grid near Hull, including seabed preparation and protection activities along the approximately 11–12 km offshore export cable route. This role was part of the construction phase of the Westermost Rough OFTO transmission assets.