Construction of the Westermost Rough transmission assets — comprising an onshore substation, an offshore substation platform, one subsea export cable, one onshore export cable and an OFTO-dedicated SCADA system — began in Q2 2013 and was scheduled to be completed around September 2014; a later ex-ante cost review noted that by early October 2014 the transmission assets were nearing the end of their construction and had been due to be fully operational by the end of September 2014.