Construction of the Westermost Rough transmission assets was completed by 18 August 2014, when National Grid Electricity Transmission issued the Completion Notice under the Generator Commissioning Clause in the Energy Act 2013. This confirmed the transmission system — comprising the offshore substation platform, subsea export cable, onshore export cable and onshore substation at Hedon — was able to transmit electricity.