cable pulling support ... diver-less installation of the array cables between the 108 turbines ... preparing ... hang-off, jointing and termination ... prepared the ROV and messenger cable
CWind provided cable pulling (pull-in) support services to CT Offshore to enable diver-less installation activities on the West of Duddon Sands offshore wind farm’s inter-array cables between the 108 turbines. CWind’s scope included preparing rigging equipment at turbine transition pieces for hang-off, jointing and termination, and supporting installation-vessel activities using an ROV and messenger cable method. CWind also provided vessels to undertake the work.