Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The inter-array cable installation campaign at West of Duddon Sands started in early June 2013, with CT Offshore’s purpose-built cable-laying vessel CLV SIA laying cables between turbines in the Irish Sea; by 25 August 2013, 54 of the planned 108 cables had been installed.