Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +0mo (May 2026): Provenance refresh (May 2026 sweep). The 2029 grid-connection target is reaffirmed in Luxcara's 25 Aug 2025 SGRE turbine-reservation PR (97 × SG 15.5 MW for Waterekke 'scheduled to connect to the national grid in 2029'), which is 384 days newer than the original BNetzA auction-award source (2024-08-13). The April 2026 debt-financing sounding (€2bn debt for €3.5-4.5bn total project cost) provides additional confirmation that the 2029 schedule remains the working baseline. Same date; refreshed source URL + source_date. --- The 1.5 GW Waterekke offshore wind farm on German site N-9.3, developed by Luxcara via Waterekke Energy GmbH, is planned to become operational and connected to the national transmission grid in 2029, with multiple sources describing this as the scheduled or earliest expected year of grid connection and operation.