Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 20 December 2011 all inter-array cables for Walney 2, connecting the turbines to the project’s offshore substation, had been safely laid on the seabed and the cable barge Stemat 82 had demobilised from the site, with only one cable termination still pending due to adverse weather conditions.