Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
After completion of repairs to the damaged export cable, the Walney 2 offshore transmission link was re-energised and operational service was restored on 20 March 2016, ending a major outage that had begun with a breakdown on 4 December 2015.