An initial seabed survey was carried out for the Walney 2 transmission export cable route, but Ofgem’s technical review later concluded that the survey was not sufficiently detailed, leaving the installation contractor inadequately informed about soil conditions and contributing to unforeseen difficulties and additional cable‑laying costs.