Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 6 August 2009, Dong Energy awarded Seabed Power two contracts to transport, lay and bury more than 92km of 33kV array cables and 44km and 43km of 132kV export cables for the UK’s Walney Offshore Wind Farm, covering both Walney 1 and Walney 2, with installation for Walney 1 scheduled to start in April 2010.