525 kV MI HVDC onshore power cable system; total cable length: 156 km + spare cable; total cable route length: 78 km.
Supply contract to provide the project's Danish onshore HVDC power cable system (525 kV MI HVDC), delivering the connection from the Danish shore to the Revsing substation. The supply contract covered the onshore cable system (manufacture in Karlskrona/Sweden) and accessories; civil works were excluded and handled by others.