Ofgem disallowed £2.0 million claimed by NGVL for payments to keep a repair vessel on standby after commissioning, finding that the assessed risk of immediate cable damage did not justify the standby vessel cost as economic and efficient. NGVL had argued that standby availability reduced the risk and potential consumer impact of a rapid repair requirement; Ofgem concluded the cost level did not meet the threshold for inclusion in allowed post‑construction costs.