Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
As part of the 2024 strategic impact assessment for Vestavind F, NVE mapped key technical and system constraints, including water depths of 200–287 metres, predominantly soft seabed sediments with localized hard masses, prevailing wind directions and gradients in energy potential, spatial variation in energy costs, and onshore grid connection limits and reinforcement needs identified together with Statnett.