In July 2015, Seajacks UK was contracted to provide its new-generation jack-up installation vessel Seajacks Scylla for the transport and installation of monopiles at the Veja Mate Offshore Wind Farm. The vessel, equipped with a Huisman 1,500 t leg‑encircling crane, will carry and install monopiles for the 67 Siemens SWT‑6.0‑154 turbines at water depths of 39–41 m in the German North Sea. The charter supports the foundations EPCI scope by enabling efficient offshore handling and installation of the very large monopiles required at the far‑shore site.